The Brief:
BNY Mellon wanted to reconfigure their existing office space from two floors to one to allow one floor to be sub-let. The construction work had to be undertaken within a working environment which meant restricted access for the construction team with much of the work being undertaken over weekends or late night working during the week.

The Solution:
Ben Johnson Ltd were appointed to deliver the project on a Design and Build basis.
The project included the construction of a new reception and meeting room suite, new business support areas including tea point areas and the reconfiguration of workstations involving the relocation of staff. All this was delivered on time, over an eight week period.

We were very pleased with the overall result and felt that the whole project had been well managed by the team, with good communication and minimal disruption.

James O'Neill, Project Manager: Property & Facilities (International)